  • Hospital front elevation, Sod, plantings, ground covering installed - Taken August 15, 2013

  • Hospital main entrance canopy, Metal panels complete, landscaping installed - Taken August 15, 2013

  • Hospital Lobby, Wall protection install, Drywall Point-up - Taken August 15, 2013

  • Hospital Area B, Nurses Station, Drywall Point-up, First clean - Taken August 15, 2013

  • Patient room corridor, Millwork installed, First clean, point-up ongoing - Taken August 15, 2013

  • Hospital Area A, Emergency room waiting, reception area, Point-up - Taken August 15, 2013

  • Hospital Area C, Signage installed - Taken August 15, 2013

  • Hospital Area C, Radiology, Equipment install - Taken August 15, 2013

  • Medical Office Building, South elevation; Storefront windows, Doors install - Taken August 15, 2013

  • Hospital roof, Roofing system top coat installed - Taken August 15, 2013

  • Hospital North elevation, Planting of trees ongoing - Taken July 19, 2013

  • Hospital Area C, R&F room equipment installation - Taken July 19, 2013

  • East elevation, Brick veneer installed - Taken May 23, 2013

  • Hospital Area A, Drywall finishing on going - Taken May 23, 2013

  • Hospital Area B, Patient room corridor, nurses station, Prime paint - Taken May 23, 2013

  • South Elevation, Weather barrier install on going - Taken March 20, 2013

  • MRI Entrance Canopy framing installed - Taken March 20, 2013

  • Fuel Tanks delivered - Taken March 20, 2013

  • Area D, Masonry interior walls complete - Taken March 20, 2013

  • Switchgear delivered, VAV installed - Taken March 20, 2013

  • Area D wall insulation - Taken March 20, 2013

  • Blocking installed - Taken March 20, 2013

  • Area D cable tray install - Taken March 20, 2013

  • Operating Room Boom plates installed - Taken March 20, 2013

  • Area B MEP rough-in on going - Taken March 20, 2013

  • Cooling Tower, RTUs delivery - Taken March 20, 2013

  • Dehumidification System - Taken March 20, 2013

  • Asphalt binder course at loop road - Taken March 20, 2013

  • March Aerial - Taken March 8, 2013

  • Front of Hospital, Exterior sheathing on going - Taken February 14, 2013

  • East Elevation, Sheathing, blocking installed - Taken February 14, 2013

  • South Elevation, Loading dock area, Masonry block installed - Taken February 14, 2013

  • CEP North Elevation, masonry block on going - Taken February 14, 2013

  • MOB North Elevation, Front Entrance - Taken February 14, 2013

  • High roof metal framing, sheathing on going - Taken February 14, 2013

  • Roof curbs, Area B - Taken February 14, 2013

  • Hospital plumbing and electrical rough-in - Taken February 14, 2013

  • Medical Mall corridor, metal framing on going - Taken February 14, 2013

  • Hospital main entrance lobby, Metal framing on going - Taken February 14, 2013

  • February Aerial - Taken February 1, 2013

  • Slab on grade pour Area B - Taken January 14, 2013

  • Slab on grade pour Area A - Taken January 16, 2013

  • Wet curing Area A and B slab - Taken January 16, 2013

  • North Elevation - Taken January 16, 2013

  • East Elevation, Metal framing ongoing - Taken January 16, 2013

  • South Elevation, Wall sheathing started line 9 - Taken January 16, 2013

  • West Elevation, Masonry block started line A - Taken January 16, 2013

  • Area C Metal framing, wall rough-in ongoing - Taken January 16, 2013

  • Area D and C, Mechanical ductwork and piping ongoing - Taken January 16, 2013

  • Area A, Roof deck poured - Taken January 16, 2013

  • MOB foundations ongoing - Taken January 16, 2013

  • North Elevation - Taken January 10, 2013

  • Roof deck concrete pour Area A and B. - Taken January 8, 2013

  • Roof deck concrete pour Area A and B - Taken January 10, 2013

  • Area B stone installed, concrete pour next week - Taken January 10, 2013

  • Area A and B Roof deck slab wet curing - Taken January 10, 2013

  • Topping out. - Taken December 20, 2012

  • Topping out. - Taken December 20, 2012

  • Topping out. - Taken December 20, 2012

  • Topping out. - Taken December 20, 2012

  • Topping out. - Taken December 20, 2012

  • Topping out. - Taken December 20, 2012

  • Topping out. - Taken December 20, 2012

  • Main Entrance canopy. - Taken December 20, 2012

  • Medical Mall corridor. - Taken December 20, 2012

  • Steel erection Areas A & B. - Taken December 20, 2012

  • Topping out beam location at medical corridor. - Taken December 20, 2012

  • Taken December 7, 2012

  • Taken December 7, 2012

  • MOB foundation excavation. - Taken December 5, 2012

  • Roof deck pour area D. - Taken December 6, 2012

  • South elevation, roof deck pour area D. - Taken December 6, 2012

  • Waterproofing installed. - Taken December 3, 2012

  • Medical Mall Corridor. - Taken December 6, 2012

  • Area B steel erection. - Taken December 6, 2012

  • North elevation. - Taken December 6, 2012

  • Area D slab on deck pour. - Taken December 4, 2012

  • Area D slab on deck prep. - Taken December 3, 2012

  • Taken October 10, 2012

  • Taken October 10, 2012

  • Taken October 2, 2012

  • Taken September 27, 2012

  • Taken September 27, 2012

  • Taken September 27, 2012

  • Taken September 27, 2012

  • Taken September 27, 2012

  • Taken September 27, 2012

  • Taken September 27, 2012

  • Taken September 27, 2012

 
FirstHealth @ Facebook.comFirstHealth @ Twitter.comFirstHealth @ Pinterest.comFirstHealth @ LinkedIn.com
Physicians Employees
Working Together, First in Quality, First in Health
Site MapPrivacy PolicyTerms & ConditionsHelp © FirstHealth of the Carolinas, Inc.