East elevation, Brick veneer installed - Taken May 23, 2013
Hospital Area A, Drywall finishing on going - Taken May 23, 2013
Hospital Area B, Patient room corridor, nurses station, Prime paint - Taken May 23, 2013
South Elevation, Weather barrier install on going - Taken March 20, 2013
MRI Entrance Canopy framing installed - Taken March 20, 2013
Fuel Tanks delivered - Taken March 20, 2013
Area D, Masonry interior walls complete - Taken March 20, 2013
Switchgear delivered, VAV installed - Taken March 20, 2013
Area D wall insulation - Taken March 20, 2013
Blocking installed - Taken March 20, 2013
Area D cable tray install - Taken March 20, 2013
Operating Room Boom plates installed - Taken March 20, 2013
Area B MEP rough-in on going - Taken March 20, 2013
Cooling Tower, RTUs delivery - Taken March 20, 2013
Dehumidification System - Taken March 20, 2013
Asphalt binder course at loop road - Taken March 20, 2013
March Aerial - Taken March 8, 2013
Front of Hospital, Exterior sheathing on going - Taken February 14, 2013
East Elevation, Sheathing, blocking installed - Taken February 14, 2013
South Elevation, Loading dock area, Masonry block installed - Taken February 14, 2013
CEP North Elevation, masonry block on going - Taken February 14, 2013
MOB North Elevation, Front Entrance - Taken February 14, 2013
High roof metal framing, sheathing on going - Taken February 14, 2013
Roof curbs, Area B - Taken February 14, 2013
Hospital plumbing and electrical rough-in - Taken February 14, 2013
Medical Mall corridor, metal framing on going - Taken February 14, 2013
Hospital main entrance lobby, Metal framing on going - Taken February 14, 2013
February Aerial - Taken February 1, 2013
Slab on grade pour Area B - Taken January 14, 2013
Slab on grade pour Area A - Taken January 16, 2013
Wet curing Area A and B slab - Taken January 16, 2013
North Elevation - Taken January 16, 2013
East Elevation, Metal framing ongoing - Taken January 16, 2013
South Elevation, Wall sheathing started line 9 - Taken January 16, 2013
West Elevation, Masonry block started line A - Taken January 16, 2013
Area C Metal framing, wall rough-in ongoing - Taken January 16, 2013
Area D and C, Mechanical ductwork and piping ongoing - Taken January 16, 2013
Area A, Roof deck poured - Taken January 16, 2013
MOB foundations ongoing - Taken January 16, 2013
North Elevation - Taken January 10, 2013
Roof deck concrete pour Area A and B. - Taken January 8, 2013
Roof deck concrete pour Area A and B - Taken January 10, 2013
Area B stone installed, concrete pour next week - Taken January 10, 2013
Area A and B Roof deck slab wet curing - Taken January 10, 2013
Topping out. - Taken December 20, 2012
Topping out. - Taken December 20, 2012
Topping out. - Taken December 20, 2012
Topping out. - Taken December 20, 2012
Topping out. - Taken December 20, 2012
Topping out. - Taken December 20, 2012
Topping out. - Taken December 20, 2012
Main Entrance canopy. - Taken December 20, 2012
Medical Mall corridor. - Taken December 20, 2012
Steel erection Areas A & B. - Taken December 20, 2012
Topping out beam location at medical corridor. - Taken December 20, 2012
Taken December 7, 2012
Taken December 7, 2012
MOB foundation excavation. - Taken December 5, 2012
Roof deck pour area D. - Taken December 6, 2012
South elevation, roof deck pour area D. - Taken December 6, 2012
Waterproofing installed. - Taken December 3, 2012
Medical Mall Corridor. - Taken December 6, 2012
Area B steel erection. - Taken December 6, 2012
North elevation. - Taken December 6, 2012
Area D slab on deck pour. - Taken December 4, 2012
Area D slab on deck prep. - Taken December 3, 2012
Taken October 10, 2012
Taken October 10, 2012
Taken October 2, 2012
Taken September 27, 2012
Taken September 27, 2012
Taken September 27, 2012
Taken September 27, 2012
Taken September 27, 2012
Taken September 27, 2012
Taken September 27, 2012
Taken September 27, 2012

